The Quechee Water Tank Project has been completed with the exception of the following items:  


•Repair of the road patch on the Quechee Hartland Road located at the bottom of the water tank access road.

•Installation of a fence along the North side of the water tank access road.

•Installation of a gate on the water tank access road.  


If you are a resident along this project and you have items that have not been addressed, please call the Public Works Office at 295-3622 to relay your concerns.  Thank you very much.


Everett Hammond (Utility Superintendent)

work # 802-295-3622    