The anticipated schedule for the remainder of the Quechee Tank Project is listed below:
- Week of 5/8/17: Clean up and restoration work will begin. Tank painting will occur by DN Tank.
- Week of 5/15/17: Quechee Hartland Road/Rte. #4 water pipe installation, disinfection and testing. Clean up and restoration work along Waterman Hill Road and the Quechee Hartland Road.
- Week of 5/22/17: Final tie in of the Quechee Hartland Road water line with the Rte. #4 water line. Clean up and restoration work along the Quechee Hartland Road.
- Week of 5/29/17: Work on punch list items.
- Week of 6/5/17: Punch list items will be completed.
- 6/9/2017: Final completion date.