Quechee Water Tank
Construction Update Notice: January 2017
The anticipated schedule for the Quechee Tank Project is listed below:
- There was a delay in filling the tank due to the painting of a couple of pipes inside the tank. The water tank construction has been and is full of water as of December 30, 2016. The tank will be tested in January to make sure it meets the drinking water standards. Due to the delay of the painting, the tank is now anticipated to be on line on or about January 10, 2017.
- The tank backfill and cleanup will likely occur into January, 2017.
- The final restoration of lawns disturbed by construction will be completed in the spring of 2017.
Please feel to call if you have any questions or concerns. Thank you very much.
Everett Hammond (Utility Superintendent)
work # 802-295-3622
email: ehammond@hartford-vt.org