The anticipated schedule through the end of October is listed below:
• There will be periodic closures of the Quechee Hartland Road to allow for the completion of the water line and paving on this road. A detour will be provided and residents along this section will have access to their properties from either end of the daily construction.
• There will be a scheduled shut down of the water main from approximately 10:00pm to 6:00am for 1 night between the middle of October and the end of October. The affected users will be notified in advance of this work.
• Water Tank construction will continue at the tank site off the Quechee Hartland Road.
NOTES
The Contractor may work Saturdays as needed through the end of the project.
Please feel to call if you have any questions or concerns. Thank you very much.
Everett Hammond (Utility Superintendent)
work # 802-295-3622