[ARCHIVED] Quechee Water Tank Construction Update Notice: Weeks of 8/08/16 and 8/15/16

Quechee Water Tank
Construction Update Notice: Weeks of 8/08/16 and 8/15/16

The anticipated schedule for the next 2 weeks is listed below:

• August 8, 2016: Test pits and pavement cutting, establishing the construction sign package.
• August 9-12, 2016: Water line installation on Waterman Hill Road, drilling and blasting of the tank site located on the Quechee Hartland Road.
• August 15-19, 2016: Water line installation on Waterman Hill Road, drilling and blasting of the tank site.

NOTE: For an updated schedule throughout the project, please visit the Town of Hartford website www.hartford-vt.org.

Waterman Hill Road and the Quechee Hartland Road will be closed to traffic during the day while water main installation is occurring. A detour will be provided and residents along this section will have access to their properties from either end of the daily construction. Please feel to call if you have any questions or concerns. Thank you very much.

Everett Hammond (Utility Superintendent)
work # 802-295-3622
email: ehammond@hartford-vt.org