To: Richard Menge, Director of Public Works
From: Allyn Ricker, Highway Superintendent
Date: June 29, 2016
Re: Paving FY 16-17
We will be starting the summer paving program sometime after July 18th. This year as part of the new CIP plan we are going to try a 10% Rubber Chip Seal on Connecticut River Road from the intersection of Sykes Mt. Avenue for about 1.9 miles. This requires shim paving on 3,750 feet, spot shims on 4,382 feet and the last 2,112 feet is direct application to the asphalt. The shim work will have to set for about 2 weeks before the application or the Chip Seal.
We will be paving the following Streets:
Aldrich Lane
Barrell Avenue
Connecticut River Rd 1
Connecticut River Rd 2
Costello Road
Credit court
Depot Street 2
Hebard Avenue
Hillside road (north)
Lantern Lane
Latham works Lane
Old River Road 1
Ozzy Lane
Quechee Main Street 3
Quechee Main Street 6
Round House Road 2
Sargent Street
South Street 2
Talbert street
Truell Road
Vermont Drive
As the summer paving is completed, we will add or subtract areas to treat as need to meet the approved budget dollars.