2023 South Main Street Parking Lot Rehabilitation

Friday September 8, 2023 Construction Update Now Available Including Information on Alternative Parking Opportunities     

Alternative Parking Opportunities Map

Friday September 1, 2023 Construction Update   

The existing municipal parking lot will be redeveloped and will consist of the following items: regrading and repaving the lot, meeting requirements of the Americans with Disabilities Act, providing access for emergency vehicles, adding lighting for safety, increasing the number of parking spaces, incorporating areas of green space to improve aesthetics, incorporating stormwater treatment practices, and relocate and add electric vehicle charging stations. The project will also include the installation of sidewalks to create a defined buffer between the parking lot and Currier Street.

The anticipated cost is between $1,250,000 and $1,500,000 with an expected construction duration of 180 days.

Current Plans Not to Be Used for Bid Purposes (PDF)     

An information meeting on the South Main Street Municipal Parking Lot Reconstruction was held on Wednesday, August 23rd at 6:00 p.m. in Room 1 of the Hartford Town Hall. For more information regarding the discussion please see the Meeting Minutes.